More road construction starts Monday

$
0
0

Another big road reconstruction is coming to the North Shore.

Starting June 15, Acres Enterprises will begin work on a $1.6 million reconstruction of Twelfth Street between Tranquille Road and Sherbrooke Avenue.

Work will run Monday to Friday from 7 a.m. to 5:30 p.m. and is expected to continue into October, with the possibility of some night or weekend work as needed.

The city is advising that partial or total closures of the road may be required during the project, and transit route No. 2 will be re-routed along Thirteenth Street for northbound passengers and Eleventh Street for those going south between Tranquille Road and Halston Avenue.

The city plans to add sidewalks to both sides of the roadway, along with improvements to drainage and lighting, and rehabilitation of the road itself.